|
The diary of FASt
May 25,
2008
Visit of the Austrian
President

May 24,
2008
The first regattas FASt
participated

After the start

With a light wind FASt
rapidly went to the front of the fleet. Then it got lost
with no wind...

The other competitors:

Roboat - the winner from
INNOC, Austria

Pinta - from the
University of Aberystwyth, UK, 2nd place

NorthStar from the
University of Queens, Canada, 3rd place
May 21, 2008
Finally the first tests
in the lake Neusiedlersee





May 20, 008
"Debug" of software in
the Yacht Clube de Breitenbrunn

Arriving to the marina.





May 18, 2008
Marina of Breitenbrunn.

The flags of
participating countries


Testing water leaks


May 18,
2008
Last details... Our house
transformed into a shipyard!


Soldering in the kitchen
with the help of the coffee machine.


May 17, 2008
Arriving to Breitenbrunn
for the 1st World Championship of Robotic Sailing, after 32h
non-stop driving and 3000km.



May 9, 2008
First "test" on the grass
with sails

April 26, 2008
Assembling the mast, keel
and bulb



April 20,
2008
Attachement of the main
hatches



April 16, 2008
The first tests with the
solar panel, battery chager and power supply


April 15,
2008
Some details of he
interior of the hull


April
14, 2008
Gluing the deck to the
hull


April 13, 2008
The
bulb: 20Kg of sheets of lead glued together with epoxy





March 20, 2008
The
backstay will fix to two pieces of stainless steel attached
to the stern panel. The same bolts also fix two 'U' shaped pieces in
carbon fiber that will be later used to install additional
hardware at the stern.


March 19, 2008
The main PCB board. This will host the main
computer, GPS, the two AD converters and all the peripheral
circuits external to the Suzaku board (logic level adapters,
buffers, status LEDs and edge connectors). The board is
approximately 20 x 12 cm.

March 19, 2008
Building a custom aluminum adapter with a CNC milling
machine. This will connect the sail motor shaft to the
motor's gear wheel with a rubber cardan joint.

Building the adapter

The complete cardan joint
March 17, 2008
More
reinforcements: a core of rigid polyurethane foam covered by
two layers of carbon fiber with epoxy. In a future boat,
these reinforcements may be done directly during the construction of
the hull.


March 5, 2008
The
central platform will support the main electronic board and
the other modules (GPS, compass, etc). The watertight
bulkhead (white) separates the stern compartment from the
rest of the hull, to prevent any leak of the rudder's shafts
of getting into the electronic boards.

March 1, 2008
The electric motors to control the sail will be mounted in the front
compartment. The motor shaft is brought to the deck through
aluminum bushings that house the ball bearings and a
watertight seal. A stainless steel piece to fix the forestay
was mounted in the bow and reinforced with a few layers of
carbon fiber.


The DC motor with the
shaft attached.

Interior view of the bow,
showing the reinforcement in the bow with carbon fiber


The deck
February
18, 2008
Internal reinforcements in plywood to support the foot of
the mast.


February 18, 2008
The
prototype of the deck. The round overture will give access
to the stern compartment where the servo motors and the
rudder mechanism will be mounted.


The solar panel (Solara
SM160M)
February 15, 2008
The
first photograh of the boat with the rudders and the keel.

February 15, 2008
Opening the overture in the bottom of the hull for the keel.



February 15, 2008
The
keel box and the two main bulkheads
February 8, 2008
The keel box was glued to
the hull with epoxy and several reinforcements of carbon
fiber and Kevlar-carbon fabric. This region of the hull was
built without the honey-comb core.


January 28, 2008
The interior of the mast
was inspected with a miniature video camera, to check the
position of the rivets that fix the rail. With the
help of a small plastic tube attached to the camera,
drops of thickened epoxy were deposited in the inner part of
the rivets in order to guarantee the stanching of the mast.

Our "high-tech" endoscope

Operating the "endoscope"

Filling the tube with
epoxy

The
inner end of one rivet...

...and after a drop of
epoxy
January 26, 2008
The keel box is
concluded. The three holes in the top will be used to fix
the keel.

January 26, 2008
The front platform where
the DC motors, batteries and power modules will be
installed.


Small bulkheads were cut
from the same material used for the deck and glued to a
Plexiglas sheet with a set of screws attached to each
bulkhead. The assembly was then glued to the bottom of the
hull.
January 26, 2008
The two rudders in their
final position.


The "nose" was made with
polyurethane rubber and is fixed to the hull with three
bolts and Sikaflex
January 20, 2008
The keel will be movable
to facilitate transportation. Similarly to dinghies, the
keel is installed in a keel box, going from the bottom of
the hull to the deck. The keel box was built in two halves,
using the keel as a mould. The two parts will be later glued
together, after fairing the internal surface to allow the
keel to slip easily with a minimum slack.

The
assembly for building one half of the keel box.

First layers of
fiberglass and polyester resin

An
essential tool to squeeze the fiber and remove the air
bubbles: a roll made up with a stack of washers.

The two halves of the
keel box in the approximate final position.
December 7, 2007
The two rudders are
controlled by two independent servomotors (Hitec HS-805BB,
27Kg.cm), connected to the rudders shafts with gear wheels.
Using two servos we will be able to vary the angle between
the rudders and even switch one servo off if the the boat is
sufficiently heeled that the windward rudder is kept out of
the water.



November 29,2007
The rudders will be
mounted in a bulkhead with bushings made of Teflon in a
stainless steel tube.

The support for the
rudders and servos.


Making the openings in
the hull for the rudders.
November 24, 2007
The mast was built with
stiff tubes of carbon fiber used in competition paddles. The
rail has been recovered from an old mast and fixed to the
tube with rivets and Sikaflex.

November 15, 2007
The core of polyurethane
rigid foam was first covered with fiberglass, faired and
then laminated in vacuum with various layers of carbon
fiber. The final keel is 1.5m long and weighs approximately
3Kg. The PVC tube runs the keel from top to bottom and may
be useful to place a sensor in the bottom of the keel.

A cut of the keel showing
the inner core of foam and wood and the outer layer of
carbon.


Testing...

After being laminating in
vacuum.

Covering the inner core with fiberglass
October 8, 2007
The
keel was built starting from a inner core of rigid
polyurethane foam, shaped to a NACA0010 profile. The core
was made in two halves, each one shaped using a custom tool:
a piece of wood cut to the desired profile and covered with
sandpaper.

The final phase of the
shaping process

Starting the shaping
process. The initial block of foam already has a wood core
and is kept in the base table with some screws.
October 3, 2007
Finally, the hull was removed from the mould!


The
dark region in the bottom does not have the honeycomb core
and is the place where the keel box will be attached.
September 29, 2007
After
3
month of interruption, the boat was finally built. The mould
was first painted with gelcoat. Then, the sandwich of carbon
fiber (outer layer), honeycomb core and fiberglass (inner
layer) was placed in the mould. A final layer of a porous
fabric was laid over the sandwich, to let the air circulate
and absorb the excess of resin. Finally, a sheet of plastic
was glued to the mould edges and the vacuum tubes attached
to it to extract the air and press the sandwich against the
hull.


A
detail of the sandwich materials.

Laying
out the sandwich layers
June 6, 2007
With
the rest of the model recovered we did the first test on the
water, just to see the boat floating.
May 25, 2007
As the polyester resin
contracts when it cures, the model was "compressed" inside
the mould. To remove it, we had to break all the frames
reducing the model only to the layer of wood stripes and
almost destroying the work of 3 months...


May 24, 2007
The fiberglass mould was
reinforced with a steel frame glued to the fiberglass.


The mould
May 12, 2007
After several iterations
of filling and sanding, the model was painted with a hard
polyurethane primer and polished to achieve a shiny surface.


April 27, 2007
Fairing the model. Algorithm is:
while (
! surface_smooth ){
fill_the_"valleys"_with_polyester_mastic;
remove_the_"hills"_with_sandpaper;
surface_smooth = complex_eye_function();
}


In the middle of the
process...

After the first coating
of filler, a sheet of fiberglass was laid on the model to
help fix the wood stripes.

The first coating of
mastic
April 19, 2007
The first trip of FASt:
from FEUP to the Elio Kayaks factory.

Arriving to Elio Kayaks

Exiting FEUP
April 17, 2007
The nose was shaped from
a block of plywood and glued to the front panel of the
model.


The nose in place.

Checking the alignment
between the nose and the hull.
April 17, 2007
After strip planking the
hull, a first layer of polyester mastic has filled the
spaces between the wood stripes. Then it was sanded to
remove the excess of filler and wood.

April 4, 2007
The hull was covered with
stripes of pine wood (20x6mm) glued to the frames. We used
thermo glue to fix the stripes and screws at the ends of the
most difficult (bended) stripes. This glue has proved to be
an efficient adhesive for this job, requiring no more than
30 seconds to cool down and fix the pieces together.




The stripes of the front
section were made of a different wood, much more flexible
than pine. Because these stripes were only 4mm thick, we
need to glue a thin 2mm layer of wood to the front frames.

Lots
of hands were necessary to keep the stripes in position!
March, 23 2007
The frames were joined to
the base table with thermo glue deposited only in the edges
of contact. It proved to be enough to keep the frames in
place and eases the process of alignment.
Because the frames have a
significant thickness (8mm), we had to place the frames at
the correct distance from the stern, according to the
frame's edge that will define the correct form of the hull:
from the stern to the maximum width of the hull, it is the
back edge of the frame that must placed at that section
coordinate; from the middle hull to the bow it is the front
edge of each frame that defines the hull shape.

In this frame, it is the
bottom part (in the picture) than defines the correct
profile of the hull.

All frames in place

Adding more frames... To
guarantee the correct distance between the frames, small
pieces of wood were glued between them.

The first frames.
February 28, 2007
Launching the first
stone!
We start by building a
solid flat table where the frames will be attached.
The frames were cut from 8mm plywood in a furniture factory,
using a CNC cutter. The input to the CNC were the drawings
of the sections exported from FreeShip, modified to include
a set of guide marks to facilitate the alignment.

The final drawings used
to cut out the frames.

The central guide.

Verifying the alignment
of the the guide with a laser beam.

The frame to support the
base platform.
|